Education Centre Parking Lot Construction Updates

Limestone Learning Foundation
Education Centre Parking Lot Construction Updates
Posted on 08/22/2023
Education Centre Parking Lot Construction UpdatesThe following information includes updates regarding the LDSB Education Centre parking lot restoration project. Please check back regularly for details.

Update: September 20, 2023

Please note the following changes to parking at the Board Office:

Fine grading of unpaved portions of parking lot has progressed faster than planned, hence moving up the paving schedule. 

Paving of current unpaved portion of parking lot is planned for Thursday, September 21. Parking will be available on current paved sections.

Paving of entire parking lot is planned for Friday, September 22 and Monday, September 25. No parking will be available on site.

Access to Education Centre will be through the front door on Friday and Monday.

Access to the Facility Services/ITS/warehouse will vary depending on progress of paving.

Update: September 18, 2023

Week of Sept. 18-22: 
  • Sidewalk and road cubs to be formed and poured
  • Fine grading of unpaved portions of parking lot
Sept. 22: 
  • Paving of current unpaved portion of parking lot
  • Parking will be available on current paved sections
Sept. 25:
  • Paving of entire parking lot planned
  • No parking will be available on site
  • Access to Education Centre will be though the front door
  • Access to Facility Services/ITS/warehouse TBD
Weeks of Sept. 25-29 and Oct. 2-6:
  • Line painting will be planned in the evening or weekend after paving completed
  • General landscaping and fencing to be completed

Update: August 22, 2023


The Limestone District School Board Education Centre parking lot has been under construction throughout July and August. While there is no good time for this type of work, we did need to address the parking lot given it has been deteriorating in recent years.

Unfortunately, while addressing storm water drainage issues, new problems emerged. The scope of the project increased, and with that, so did the noise from additional rock breaking. We know this has been disruptive to the community and we apologize for the inconvenience. Fortunately, we believe most of this type of work is now behind us. Paving is scheduled to start the week of August 28 which should be less disruptive. Moving forward, we will post project updates to this page so you can have an up-to-date look at timelines.

We thank you again for your patience and understanding.